The
following is an outline of what you can expect during the
construction of your in ground pool, a process that can
take from as little as 2 weeks to as much as 6 months, depending
on the scope of the project.
1)
Initial meeting and consultation - The owner of Avoca
Pools & Landscape Inc., Shaun McDonald, will come out
to your home and meet with you to discuss your wants and
needs and give you advice and information regarding your
intended project. He will listen carefully to your ideas
with a view to incorporating them into your own personal
custom design. If warranted, and dependant upon the size
and scope of your project, he will then ask our Landscape
Design Architect to meet with you for further discussion.
2) Project design, approval and cost estimate - This
is where we take your ideas and wishes and meld them into
a pool and/or landscape design worthy of your property.
Once we have a completed scale drawing, we will send it
to you for your approval. Now is the time to make any changes
to the design. Once approval is given by you, estimation
of cost will commence.
3) Permit approval and signing of Contract - Once
we have priced your project and this has been accepted by
you, a contract is drawn up outlining every aspect of the
job. This contract must be signed and once this is done,
permit approval from the relevant city department can be
pursued. Depending upon municipality, this can take from
1 day to 4 weeks.
4) First payment as per Contract due and payable
5) Layout of pool and Environs included in contract
- Once all applicable permits are obtained, the location
of the pool is marked to scale on the existing ground. Any
other areas that require excavation will be laid out at
this time, as will any trenches etc. required for plumbing
and electrical. This is the last opportunity to make any
changes as the following day excavation will commence. The
layout of the pool will be exactly 2' larger than the finished
pool itself due to the need for a 24" over-dig.
6) Second payment as per Contract due and payable
7) Excavation, steel wall placement, concreting -
The excavation is the messiest part of the whole job and
it can sometimes concern clients who are not familiar with
in ground pool construction. This only lasts for a couple
of days at most so please don't get discouraged. In order
for the liner to be installed successfully into the finished
pool without any wrinkles, the hole has to be excavated
very precisely to exact specifications. Whilst the hole
is progressing the steps and heavy steel walls of the pool
will be erected, squared and leveled. The slope inside the
pool from the shallow end to the deep end as wall as the
ones in the deep end bowl are trimmed and finished and the
pool is ready for concreting.
For the footing material placed around the walls and under
the steps, as well as the 2" rough coat we trowel onto
the whole bottom of the pool, we use fiberglass reinforced
25mpa concrete. The fiberglass is mixed in with the concrete
and gives it a huge amount of additional strength, equivalent
to that provided by 4" wire mesh. The rough coat on
the bottom of the pool provides both protection for the
slopes from wet weather and increases the structural integrity
of the pool, ensuring that you will get the best return
on your investment for years to come. The pool will now
sit for at least one day for the concrete to set up prior
to back filling.
8) Backfilling and Plumbing/Electrical - After the
concrete has set up, braces are placed across the width
of the pool to prevent any movement of the tops of the walls
whilst backfilling takes place. Granular material is then
brought in by the truckload and carefully placed and compacted
around the perimeter of the pool. Once backfilling reaches
the level of the skimmer and returns (and any other accessories
such as underwater lights) plumbing lines and electrical
conduit are run to the area where pump, filter and electrical
outlets will be located. Avoca Pools & Landscape Inc.
takes great care during the backfilling process to ensure
that no settling takes place at a later date. This process
takes approximately 2 full days to bring the fill up to
final grade; this however is dependant upon how much fill
is required. (determined by how level the existing ground
was prior to pool installation)
9) Coping Installation - Dependant upon the type
of coping you have chosen, this can take from half a day
to upwards of 3-4 days.
10) Pool Deck - Once again, this depends on what
type of pool deck your design calls for. If 36" poured
concrete with brush finish, one and a half days will see
it formed, poured and finished. However, choosing more elaborate
pool deck surrounds such as interlocking brick or natural
stone will increase the time it takes to finish this part
of the project.
11) Landscaping/ Entertaining areas/ Fencing - The
time it can take for this aspect of the job varies widely
depending upon how much is involved. Your contract will
spell out terms and conditions relating to your specific
project, including the approximate duration of the construction
period.
12) Final grout coat on pool floor - This is the
final procedure before installing the liner and filling
your pool with water. A 1"-2" layer of smooth
cement/vermiculite grout is trowelled over the rough concrete
coat to the exact elevations and measurements as required
by the liner specifications. This creates the hard, smooth
bottom of the pool that you feel under your feet when you
are swimming. This takes 1 day however, if wet weather is
forecast, this will be delayed until more favorable conditions
are anticipated.
13) Liner Installation - Preferably the day of the
liner installation should be sunny and warm in order to
help stretch the liner into place. Once installed into the
retainer track running around the perimeter of the pool
a large vacuum is placed between the liner and the wall
in the deep end. This vacuum pulls the liner into place
and at this stage water trucks start filling up the pool.
The vacuum is not removed until the water is at least 6"
into the shallow end. Return and skimmer face plates are
attached and the liner is cut out. Water is then brought
up to start-up level. (about half way up skimmer opening)
14) Pool Start-up - Once water is at start-up level
the pump can be primed and started and the pool can begin
operating. The water will be initially treated with chemicals
or salt (if salt water chlorination system is installed).
Please note; if the electrical work is not included in our
contract, this must be done by this stage so that we may
operate the system. Personal instructions will be provided
to you on your pool, pool equipment, pool maintenance and
water chemistry.
15) Clean up - Our crews will leave your property
the way it was when we first arrived. We will grade and
sod or seed all access areas if included in your contract.
All construction waste will be removed and disposed of.
Streets and driveways will be swept clean. Dust from construction
will be cleaned off the outside of your house. We endeavour
to make it appear as though we were never there.
16) Final payment - The final payment as per the
signed contract is due at this time. There will be no holdback
unless stated otherwise in your contract.